Numerical Method of Determining Installation Force for Parallel Strand Cables

Zhang Zhuo- jie Wang Rong- hui   

  1. School of Civil Engineering and Transportation,South China University of Technology,Guangzhou 510640,Guangdong,China
  • Received:2013-06-06 Revised:2013-10-16 Online:2014-02-25 Published:2014-01-02
  • Contact: 张卓杰(1986-),男,博士生,主要从事大跨度桥梁结构理论研究. E-mail:civilzhangzhuojie@163.com
  • About author:张卓杰(1986-),男,博士生,主要从事大跨度桥梁结构理论研究.
  • Supported by:

    国家自然科学基金资助项目(51378220)

Abstract:

Based on the basic stretch- draw principle of parallel strand stay cables,formulas respectively describingthe configuration of target state and the unstressed cable length were set up according to the catenary theory.Then,two problems existing in the stretch- draw process of parallel strand stay cables were put forward,and the corre-sponding solving methods were proposed and a calculation program was compiled with Matlab to determine the sin-gle strand initial tension.Finally,a case study on the Tongling rail- road cable- stayed bridge under construction wasconducted.The results show that the proposed method is effective and reliable,and that it may provide theoreticalreferences for the construction of parallel strand stay cables.

Key words: parallel strand stay cable, cable force, isotension method, numerical calculation